The Colorado based Ball Corporation’s Pittston, PA facility is a state-of-the art manufacturing plant focused on the production of aluminum beverage packaging. The project was a significant undertaking, as MYCO handled all of the ductwork and HVAC equipment, regulating and controlling air exchange and cooling through the whole facility, as well as plumbing functions including large scale underground work.

Challenge

As a newly built facility with complex systems throughout the interior, exterior, and underground of the building, teams had to work diligently to maneuver layouts, logistical measures, and coordination with other contractors on site.

The scale of the building called for extensive duct work installation which can be materially and logistically challenging to pull off effectively.

Solution

MYCO’s Virtual Design and Construction (VDC) team took 3D scans from inside the building and from the rooftop to coordinate underground and materials that went through to the roof. This allowed for systems and materials to be carefully laid out pre-installation. This approach allowed for easy collaboration between MYCO, the designer, and other contractors. It also gave a concise roadmap of functions and applications that allowed for a smooth installation process once construction began.

VDC Walkthrough

VDC Walkthrough

VDC Walkthrough

VDC Walkthrough

|

Installation

Installation

|

MYCO’s prefabrication team also assembled extensive mechanical piping and duct to maneuver challenging on-site installation. This, in turn, created a safer environment and easier assembly on-site all while adding layers of quality control. The prefabrication team was also able to utilize one of MYCO’s additional storage facilities to house large materials as they awaited installation, this eased the coordination process for materials and made for a faster installation process.

Sucessful Outcome

The facility came together excellently and is a standout feature of the local economy. This project was a major steppingstone in MYCO’s advancement in cutting-edge technology as the digital coordination efforts utilized streamlined coordination and construction processes. This was the benchmark for the revamping of MYCO’s technological systems through projects with the hopes of streamlining communication, making installation more efficient, and giving teams tools to create an all-around safer working environment.

Previous Case Study

Del Grosso Food Retort

The DelGrosso Foods Retort project in Altoona, PA was an HVAC & plumbing project that aimed to implement a state-of-the-art steam, hot water, and cooling system.

Next Case Study

Providence Place Mall

This was a complex project to replace twenty-three rooftop units for a shopping mall. The large heavy units were located on the roof of the mall in such a way that we needed to use a Sikorsky S-64 Skycrane helicopter to replace them.